Project description: Construction of wind turbines in Aneby and Jönköping municipalities
Number of works: 24 pieces
Total effect: up to XNUM MW
Operating Status: Permission is available to build 24 plants, of which 4 plants in Haurida Västra (concession for connection Ramsjöholm) and 12 plants in Knohult and 8 plants in Älgön (concession for connection Barkeryd).
Detailed engineering completed for Knohult and Älgön in 2020 and infrastructure work is expected to start in 2021. Planned operation starts in 2022.
For further information about the establishment Knohult / Älgön see website www.vindinvedbo.se